Beginning Thursday, April 23, 2020 at 5:00PM until Monday, April 27, 2020 at 5:00AM Contract Operator will be restriping and resealing the cross-spine. In addition, crosswalks will be added from 9032 (south side of cross spine) at the doorways to the designated walkway along 9022 (the north side). To accomplish this, the cross spine will be closed the entire duration, except for emergency exiting only, to allow for paint and sealant drying.

Work will be done per the following schedule:

     1. 4/23 Prep work - stripping and cleaning the floor after 5pm
     2. 4/24 Cross Spine closed to all traffic at 3pm
          a. NOTE: this also includes the entry points at the spine/cross spine intersection
     3. 4/24 After 3pm start painting the walkways and cross walks – starting West to East
     4. 4/26 Complete sealing of cross spine
     5. 4/27 Open to normal traffic at 5am