Cross Spine Skylight Work October 4-18, 2019

Starting October 4, 2019 through October 18, 2019, work will be performed in the West Cross Spine near the skylights. This work will require closure of the area when there is a risk of debris falling through the openings. The related work is planned to be performed after hours between 4:00 P.M. and 5:00 A.M. When the areas are closed off, there will be barricades and caution tape to indicate the blocked off areas. Vehicle and foot traffic will not be allowed through the barricaded areas. Normal access must be either from the east or west but not through the Cross Spine.

Contract Operator works diligently to ensure the safety of all site Occupants including contractors working in closed areas. Please be mindful of workmen and obey all traffic control.

If you should have any questions please do not hesitate to contact Shelly Jost at Occupantservices@uastp.com. In addition, please visit www.uastp.com to stay informed on recent operations advisory announcements.